2023 Revitalization Project

2024-05-16 Update

Re-roofing work is continuing on the buildings in the south west of the community. 27 out of 52 buildings have been completed.

2024-02-15 Update

Approximately 22 buildings have been re-roofed. The video below was taken February 7th after 3 days of rain. The weather has temporarily slowed progress, but the crews are expected to be back at work towards the end of the month.

2024-01-28 Update

Approximately 20 buildings have been re-roofed, or 38% of the community. Antis, the roofing contractor, is currently working on the west side of the community. They will continue in a counter-clockwise direction until complete.

Video

2024-01-14 Update

14 out of 52 buildings have been re-roofed. The 5846 Creekside cul-de-sacs are almost complete.

Video

2024-01-01 Update

Happy New Year. The re-roofing project is moving along with 10 out of 52 buildings done, or about 19% complete. The roofs of the cul-de-sac at 5846 Creekside #29-44 are shown below.

Video

2023-12-04 Update

Phase 1 is complete. Phase 2, the final phase to re-roof the remaining buildings, has started. The construction will go in order from building 1 to building 47, roughly counter-clockwise around the community. Please see the revised map for details.

Roofs for 222 N Singingwood #1-2 and #3-6 are complete

Video

2023-11-16 Update

Phase 1 is underway. Re-roofing has started for:

  • Building 7 – 5846 E Creekside #25-28
  • Building 16 – 222 N Singingwood #3-6
  • Building 17 – 222 N Singingwood #1-2
  • Building 35 – 152 N Singingwood #1-2
  • Building 45 – 5727 E Stillwater #3-6

Building #7 is pictured below

2023-09-12 Update

The ballots have been counted. The association received 99 ballots out of a possible 166. The results were 72 Yes votes and 27 No votes.
The Yes votes have the majority, the project is approved.

The Board would like to thank the members for participating in the vote. More information on next steps will be provided as it becomes available.

Click here to view the recording of the meeting and ballot counting on Youtube

2023-08-17 Update

We did not have enough votes to make quorum. The opening of the ballots has been postponed until September 12th at 6:00pm.

2023-07-12 Update

The board would like to thank all the home owners that attended the Town Hall. A link to the recording of the meeting and a copy of the slideshow presentation are available below:

2023-05-25 Update

The board, Powerstone management, and Ross Construction are in the early phases of planning a new project after the community rejected the 2022 project.

The areas of improvement are focused solely on water intrusion related issues:

We are still finalizing estimates, the cost will be around $3 million and require a loan.

Tentative Timeline

DateItemAdditional Information
2023-05-24Flyer 1, e-blast2023-project-flyer-1.png
2023-06-02Flyer 2, e-blast2023-project-flyer-2.png
2023-06-07MeetingZoom, Volunteer Education
2023-06-26Flyer 3, e-blast2023-project-flyer-3.png
2023-06-28MeetingZoom, Executive Town Hall Prep
2023-07-05MeetingZoom, Executive Town Hall Prep
2023-07-12MeetingZoom, Town Hall
2023-07-13Flyer 4, e-blast2023-project-flyer-4.png
2023-07-17Ballots Mailed
2023-07-26MeetingIn person – club house, Q&A
2023-08-17MeetingIn person – club house, Count Ballots